Construction Update Archive

Check here for past construction information and join our email list for regular updates.

December 2023 Road Closures

Broadway Corridor Lower Segment (East Houston Street to IH-35) & Avenue B and North Alamo Bike Lanes Broadway (E. Jones to Roy Smith)

  • Westside roadway reconstruction continues thru January 2024, including curbs, sidewalks, driveway approaches, and pavers.
  • Two-Way traffic northbound and southbound is opened, and will be maintained while working on the west side of the roadway.

9th Street (Broadway to North Alamo) and 9th Street (Broadway ½ block west to Avenue B)

  • A full road closure continues thru December 8, 2023 weather permitting
  • Broadway remains open to northbound and southbound traffic.
  • Sundt construction continues CPS overhead to underground conversion, boring underneath Broadway at 9th Street, and installing a duct bank.
  • West of Broadway is closed up to Augie’s BBQ driveway on 9th Street. The driveway will remain open. Augie’s BBQ new driveway on Broadway will be open, with two access points at all times.
  • East of Broadway will be closed to the alleyway. 9th Street is open to alleyway from N. Alamo. Sidewalks will remain open. Grunt Style and New Western Acquisition will have access to their driveways on Broadway.

Broadway (Brooklyn Ave. to 6th St.) and (McCullough Ave, to 4th St.)

  • Full road closure continues thru December 2023 (McCullough Ave. will remain open to eastbound and westbound traffic throughout these closures)
  • Pedestrians will have access along existing sidewalks on all sides, and a detour route will provide access to businesses and alternate routes throughout the closures.

Broadway (Brooklyn Ave. to 6th St.) and (McCullough Ave. to 4th St.)

  • Sidewalk work with traffic access northbound and southbound will be open during the December 2023 Holidays
  • Businesses and driveway access will be maintained

Broadway (6th St. to McCullough) and (4th St. to Pecan)

  • A full road closure from January 2024 thru March 2024 (4th St, 6th, and Brooklyn will remain open to eastbound and westbound traffic throughout these closures)
  • Pedestrians will have access along existing sidewalks on all sides, and a detour route will provide access to businesses and alternate routes throughout the closures.

Broadway (Brooklyn Ave. to 6th St.) and (McCullough Ave, to 4th St.)

  • Sidewalk work with traffic access northbound and southbound will be open starting January 2024 thru March 2024
  • Businesses and driveway access will be maintained

Project Notes:

Contractor Sundt Construction continues roadway reconstruction on theBroadway Corridor Lower Segment (E. Houston St. to IH-35) project, and bike lane work on the Avenue B and N. Alamo Bike Lane project.

  • Avenue B, McCullough, and N. Alamo bike lanes are completed
  • AT&T work throughout the project is completed
  • All work is weather permitting, construction scheduling adjusted daily as needed by Sundt

This work is associated with the $42 Million, 2017 Bond Project. Businesses and residents have sidewalk and parking lot accessibility. Bike lane work is in association with the Avenue B/North Alamo bike lanes. Access to local traffic and businesses will be maintained. Please see the road closures and detour route maps provided.

October 2023 Road Closures

Brooklyn & Avenue B – Intersection work

  • Sundt Construction will start work at the intersection of Brooklyn & Avenue B as early as October 16, 2023 thru October 20, 2023
  • Work includes replacing the raised median at the intersection with a rollover curb, and modifying another median to the south to create a better turning radius for fire engines
  • This work will require a one day closure at the southern part of the intersection for either October 18th or 19th
  • Avenue B southbound traffic will be detoured west on Brooklyn to St. Mary’s, then southeast on McCullough for one day or as needed
  • Flagmen will be on site to facilitate traffic as needed
  • All work is weather permitting, and the dates of the work may be extended due to unforeseen occurrences.

South Alamo Street & E. Cesar E. Chavez Blvd. Intersection Closure

Beginning Monday, October 2, 2023, South Alamo Street will be closed to northbound and southbound traffic at E. Cesar E. Chavez Blvd. through mid-November 2023. E. Cesar E. Chavez Blvd. will remain open to westbound and eastbound traffic. Due to weather or unforeseen conditions the closure date may be extended. Work in the area will include drainage construction for the project.

The south side of E. Cesar E. Chavez Blvd. will be closed for 3 weeks in phase 1, and traffic will be detoured and shifted to the north side, utilizing one lane in each direction. After phase 1 is completed, the north side of E. Cesar E. Chavez Blvd. will be closed for 2 weeks in phase 2. The traffic will be detoured and shifted to the south side to complete the drainage construction on the north side of E. Cesar E. Chavez Blvd. Signage will alert drivers of the detour routes.

Throughout the closures, pedestrians will have access along existing sidewalks and all businesses will remain accessible. See detour maps provided.

9th Street (Broadway to North Alamo) and 9th Street (Broadway ½ block west to Avenue B):

Has been rescheduled to start Friday, October 13, 2023

  • A full road closure will start as early as Friday, October 13, 2023 thru early December 2023
  • Broadway remains open to northbound and southbound traffic.
  • Sundt construction will be working on CPS overhead to underground conversion, boring underneath Broadway at 9th Street, and installing a duct bank.
  • West of Broadway will be closed up to Augie’s BBQ driveway on Ninth. The driveway will remain open. Augie’s BBQ new driveway on Broadway will be open, with two access points at all times.
  • East of Broadway will be closed all the way to N. Alamo. The alley mid-block will be closed to traffic. Sidewalks will remain open. Grunt Style and New Western Acquisition will still have access to their driveways on Broadway Street.
  • See attached detour map provided.

Intersection of Broadway & Brooklyn Ave. to the Intersection of Broadway & 6th St. and McCullough Ave, to the intersection of Broadway & 4th St.: 

  • Full road closure September 2023 thru December 2023 (McCullough Ave. will remain open to eastbound and westbound traffic throughout these closures)
  • Pedestrians will have access along existing sidewalks on all sides, and a detour route will provide access to businesses and alternate routes throughout the closures.
  • See attached detours maps

 

Project Notes:

Contractor (Sundt Construction) continues reconstruction work on the South Alamo Street (Market Street to East Cesar E. Chavez Blvd.) project. To facilitate traffic, there will be at least one lane open in each direction for through traffic from Market Street to East Cesar E. Chavez Blvd.

Contractor Sundt Construction continues roadway reconstruction on the Broadway Corridor Lower Segment (E. Houston St. to IH-35) project, and bike lane work on the Avenue B and N. Alamo Bike Lane project.

  • Broadway (Brooklyn to Roy Smith): Work includes westside roadway reconstruction, including curbs, sidewalks, driveway approaches, and pavers.
  • Broadway (E. Jones to Roy Smith): CPS Duct Bank work completed. Westside roadway reconstruction, including curbs, sidewalks, driveway approaches, and pavers. Two-Way traffic northbound and southbound is opened, and will be maintained while working on the west side of the roadway.
  • AT&T work throughout the corridor is completed.
  • Avenue B, McCullough, and N. Alamo bike lanes: Miscellaneous work, clean-up work, and pressuring washing.
  • All work is weather permitting, construction scheduling adjusted daily as needed by Sundt.

This work is associated with the $42 Million, 2017 Bond Project. Businesses and residents have sidewalk and parking lot accessibility. Bike lane work is in association with the Avenue B/North Alamo bike lanes. Access to local traffic and businesses will be maintained. Construction began Summer 2020 and will be substantially complete by Summer 2024. For ease of reference a list of road closures and detour route maps are provided.

 

Current and planned work:

  • Installation of AT&T duct bank across S. Alamo at Nueva is to be completed by 9.21.23
  • AT&T continuing copper splicing between Nueva and Cesar Chavez
  • Continuing construction of CPS Vault; Sundt currently working on walls and deck
  • Excavation and installation of chilled water between Nueva and La Villita west side of S. Alamo
  • Installing Temporary Water System on east side of S. Alamo south of Nueva intersection

This work is associated with South Alamo (Market Street to East Cesar E. Chavez Blvd.) 2017 Bond Project. To facilitate traffic, there will be traffic control signage available to direct motorists. Businesses and residents will have sidewalk and driveway accessibility. Sidewalk closures are marked with signage for alternate routes. Public Works will continue to communicate any changes as the project progresses. Project construction began December 2022 and is anticipated to be substantially complete by Early 2025.

September 2023 Road Closures

Broadway Corridor Lower Segment

(East Houston Street to IH-35) & Avenue B and North Alamo Bike Lanes

Intersection of Broadway & Brooklyn Ave. to the Intersection of Broadway & 6th St. and McCullough Ave, to the intersection of Broadway & 4th St.: 

  • Full road closure September 2023 thru December 2023 (McCullough Ave. will remain open to eastbound and westbound traffic throughout these closures)
  • Pedestrians will have access along existing sidewalks on all sides, and a detour route will provide access to businesses and alternate routes throughout the closures.
  • See attached detours maps

Project Notes:

Contractor Sundt Construction continues roadway reconstruction on the Broadway Corridor Lower Segment (E. Houston St. to IH-35) project, and bike lane work on the Avenue B and N. Alamo Bike Lane project.

  • Broadway (Brooklyn to Roy Smith): Work includes westside roadway reconstruction, including curbs, sidewalks, driveway approaches, and pavers.
  • Broadway (E. Jones to Roy Smith): CPS Duct Bank work completed. Westside roadway reconstruction, including curbs, sidewalks, driveway approaches, and pavers. Two-Way traffic northbound and southbound is opened, and will be maintained while working on the west side of the roadway.
  • Broadway & E. Jones Intersection: The intersection is opened to northbound and southbound traffic. Eastbound and westbound traffic remains closed thru August 2023. Full reconstruction work includes: CPS distribution duct bank installation completed. CPS overhead to underground conversion duct bank continues, storm drain and structures, new CPS roadway illumination, new COSA pedestrian illumination and traffic signals, irrigation, low impact drainage, adjustments to valves and manholes, and asphalt paving.
  • AT&T work throughout the corridor is completed.
  • Avenue B, McCullough, and N. Alamo bike lanes: Clean-up work, and pressuring washing.
  • All work is weather permitting, construction scheduling adjusted daily as needed by Sundt.

This work is associated with the $42 Million, 2017 Bond Project. Businesses and residents have sidewalk and parking lot accessibility. Bike lane work is in association with the Avenue B/North Alamo bike lanes. Access to local traffic and businesses will be maintained. Construction began Summer 2020 and will be substantially complete by Summer 2024. For ease of reference a list of road closures and detour route maps are provided.

August 2023 Road Closures

Broadway Corridor Lower Segment (East Houston Street to IH-35) & Avenue B and Alamo Bike Lane

Broadway & E. Jones Intersection Closure:

  • Broadway at E. Jones intersection is opened to northbound and southbound traffic. Eastbound and westbound traffic remains closed thru August 2023.

Project Notes:

Contractor Sundt Construction continues roadway reconstruction on the Broadway Corridor Lower Segment (E. Houston St. to IH-35) project, and bike lane work on the Avenue B and N. Alamo Bike Lane project.

  • Broadway (Brooklyn to Roy Smith) work includes westside roadway reconstruction, including curbs, sidewalks, driveway approaches, and pavers.
  • Broadway (E. Jones to Roy Smith) CPS Duct Bank work continues. Two-Way traffic northbound and southbound is opened, and will be maintained while working on the west side of the roadway.
  • Broadway & E. Jones Intersection full reconstruction work includes: street excavation, CPS distribution duct bank installation, CPS overhead to underground conversion duct bank, storm drain and structures, new CPS roadway illumination, new COSA pedestrian illumination and traffic signals, irrigation, low impact drainage, adjustments to valves and manholes, and asphalt paving.
  • AT&T work throughout the corridor is completed.
  • Avenue B, McCullough, and N. Alamo bike lane work continues with installation of bike lane dividers.

This work is associated with the $42 Million, 2017 Bond Project. Businesses and residents have sidewalk and parking lot accessibility. Bike lane work is in association with the Avenue B/North Alamo bike lanes. Access to local traffic and businesses will be maintained. Construction began on July 2020 and will be substantially complete by June 2024. For ease of reference a list of road closures and detour route maps are provided.

July 2023 Road Closures

Broadway Corridor Lower Segment  (East Houston Street to IH-35)
Avenue B and North Alamo Bike Lanes 

Broadway (West Side Intersections at 8th, 9th & 10th Street) – Temporary Road Closure Week of 4.17.23

    • Broadway West Side Intersections at 8th, 9th & 10th Street will be will be temporarily closed starting as early as the week of 4.17.23 thru 5.1.23 for roadway reconstruction, and asphalt paving.
    • Northbound, southbound, and eastbound traffic to remain open at all intersections.

Avenue B / McCullough / North Alamo Bike Lanes

    • Landscaping, signage installation, and roadway striping continues. Flagmen will be onsite as needed to help direct traffic at intersection areas, and roadways are opened to traffic.

Broadway Corridor Lower Segment (E. Houston St. to IH-35):

    • Sundt Construction continues roadway reconstruction on Broadway (Brooklyn to Roy Smith) thru August 2023. Two-way traffic north and south is opened to traffic, and will be maintained while working on the west side of the roadway. In addition, and concurrent with this work, the contractor will be working on Broadway (West Side Intersections at 8th, 9th & 10th Street), and will be will be temporarily closed starting as early as the week of 4.17.23 thru 5.1.23 for roadway reconstruction, and asphalt placement.
    • AT&T work continues throughout the corridor.
    • SAWS water main installation on Broadway (Peacock Alley Intersection to E. Houston) is completed, and opened to traffic.

Road closures and alternate routes are made monthly.
Check here for the most up-to-date information and join our email list for regular updates.

ROAD CLOSURES:

    • Broadway & E. Jones Intersection: Intersection will be fully closed thru July 2023.
    • Broadway & E. Jones Intersection: End of July 2023 the intersection will be opened on Broadway to northbound and southbound traffic, with E. Jones closed to eastbound and westbound traffic.
    • Broadway (E. Jones to Roy Smith): August 2023 thru September 2023 (Two-Way traffic north and south opened, and will be maintained while working on the west side of the roadway)

June 2023 Road Closures

Broadway Corridor Lower Segment  (East Houston Street to IH-35)
Avenue B and North Alamo Bike Lanes 

Broadway (West Side Intersections at 8th, 9th & 10th Street) – Temporary Road Closure Week of 4.17.23

    • Broadway West Side Intersections at 8th, 9th & 10th Street will be will be temporarily closed starting as early as the week of 4.17.23 thru 5.1.23 for roadway reconstruction, and asphalt paving.
    • Northbound, southbound, and eastbound traffic to remain open at all intersections.

Avenue B / McCullough / North Alamo Bike Lanes

    • Landscaping, signage installation, and roadway striping continues. Flagmen will be onsite as needed to help direct traffic at intersection areas, and roadways are opened to traffic.

Broadway Corridor Lower Segment (E. Houston St. to IH-35):

    • Sundt Construction continues roadway reconstruction on Broadway (Brooklyn to Roy Smith) thru August 2023. Two-way traffic north and south is opened to traffic, and will be maintained while working on the west side of the roadway. In addition, and concurrent with this work, the contractor will be working on Broadway (West Side Intersections at 8th, 9th & 10th Street), and will be will be temporarily closed starting as early as the week of 4.17.23 thru 5.1.23 for roadway reconstruction, and asphalt placement.
    • AT&T work continues throughout the corridor.
    • SAWS water main installation on Broadway (Peacock Alley Intersection to E. Houston) is completed, and opened to traffic.

Road closures and alternate routes are made monthly.
Check here for the most up-to-date information and join our email list for regular updates.

ROAD CLOSURES:

    • Broadway & E. Jones Intersection: Intersection will be fully closed thru July 2023.
    • Broadway & E. Jones Intersection: End of July 2023 the intersection will be opened on Broadway to northbound and southbound traffic, with E. Jones closed to eastbound and westbound traffic.
    • Broadway (E. Jones to Roy Smith): August 2023 thru September 2023 (Two-Way traffic north and south opened, and will be maintained while working on the west side of the roadway)

May 2023 Road Closures

Broadway Corridor Lower Segment  (East Houston Street to IH-35)
Avenue B and North Alamo Bike Lanes 

Broadway (West Side Intersections at 8th, 9th & 10th Street) – Temporary Road Closure Week of 4.17.23

    • Broadway West Side Intersections at 8th, 9th & 10th Street will be will be temporarily closed starting as early as the week of 4.17.23 thru 5.1.23 for roadway reconstruction, and asphalt paving.
    • Northbound, southbound, and eastbound traffic to remain open at all intersections.

Avenue B / McCullough / North Alamo Bike Lanes

    • Landscaping, signage installation, and roadway striping continues. Flagmen will be onsite as needed to help direct traffic at intersection areas, and roadways are opened to traffic.

Broadway Corridor Lower Segment (E. Houston St. to IH-35):

    • Sundt Construction continues roadway reconstruction on Broadway (Brooklyn to Roy Smith) thru August 2023. Two-way traffic north and south is opened to traffic, and will be maintained while working on the west side of the roadway. In addition, and concurrent with this work, the contractor will be working on Broadway (West Side Intersections at 8th, 9th & 10th Street), and will be will be temporarily closed starting as early as the week of 4.17.23 thru 5.1.23 for roadway reconstruction, and asphalt placement.
    • AT&T work continues throughout the corridor.
    • SAWS water main installation on Broadway (Peacock Alley Intersection to E. Houston) is completed, and opened to traffic.

This work is associated with the $42 Million, 2017 Bond Project. Businesses and residents have sidewalk and parking lot accessibility. Bike lane work is in association with the Avenue B/North Alamo bike lanes. Access to local traffic and businesses will be maintained. Construction began on July 2020 and will be substantially complete by June 2024. For ease of reference a list of road closures and detour route maps are provided.

ROAD CLOSURES:

    • Broadway (Brooklyn to Roy Smith) Thru April 2023 (Two-Way traffic north and south will be maintained while working on the west side of the roadway)
    • Broadway (West Side Intersections at 8th, 9th & 10th Street) – Temporary Road Closure week of 4.17.23 thru 5.1.23 (Northbound, southbound, and eastbound traffic to remain open at all intersections)
    • Broadway (Brooklyn to Roy Smith) April 2023 thru June 2023 (Two-Way traffic north and south will be maintained while working on the west side of the roadway)

April 2023 Road Closures

ROAD CLOSURES:

  • Broadway (Peacock Alley Intersection to E. Houston) Thru April 7, 2023
  • Broadway (Brooklyn to E. Jones) Thru August 2023 (Two-Way traffic north and south will be maintained while working on the west side of the roadway)
  • Broadway West Side Intersections at 9th, 8th & 10th Street – Temporary Road Closure Week of 3.20.23 (Northbound, southbound, and eastbound traffic to remain open at all intersections)
  • Broadway (E. Jones to Roy Smith) Work starts April 2023 thru August 2023 (Two-Way traffic north and south will be maintained while working on the west side of the roadway)

March 2023 Road Closures

ROAD CLOSURES:

  • Avenue B (E. Jones to Roy Smith) February 27, 2023 – Completed
  • Broadway (Travis to Peacock Alley) thru March 3, 2023
  • Broadway (Peacock Alley Intersection to E. Houston) starts March 3, 2023 thru April 7, 2023
  • Broadway (Brooklyn to E. Jones) February 2023 thru April 2023 (Two-Way traffic north and south will be maintained while working on the west side of the roadway)

February 2023 Road Closures

ROAD CLOSURES:

Broadway (Brooklyn to E. Jones)
thru February 2023

Broadway (Travis Intersection to Peacock Alley)
thru February 3, 2023

Broadway (Peacock Alley to E. Houston)
February 3, 2023 thru February 17, 2023

Broadway (Brooklyn to E. Jones)
March 2023 thru June 2023

Broadway (McCullough to Brooklyn)
March 2023 thru June 2023

Mid-December 2022 Road Closures

ROAD CLOSURES:

Broadway (Brooklyn to E. Jones) 

Current thru January 2023

Broadway (Travis to E. Pecan) 

Current thru December 2, 2022

Broadway (Travis Intersection to Peacock Alley) 

January 3, 2023 thru January 25, 2023

Broadway (Peacock Alley to E. Houston) 

January 26, 2023 thru February 17, 2023

Broadway (Brooklyn to E. Jones) 

January 2023 thru February 2023

December 2022 Road Closures

ROAD CLOSURES:

Broadway (Brooklyn to E. Jones) 

Current thru January 2023

Broadway (Travis to E. Pecan) 

Current thru December 2, 2022

Broadway (Travis Intersection to Peacock Alley) 

January 3, 2023 thru January 25, 2023

Broadway (Peacock Alley to E. Houston) 

January 26, 2023 thru February 17, 2023

Broadway (Brooklyn to E. Jones) 

January 2023 thru February 2023

August 2022 Road Closures

Broadway (3rd to McCullough) and McCullough (N. Alamo to Avenue B)
June 2022 thru August 2022

Broadway (Brooklyn to E. Jones)
June 2022 thru October 2022

Broadway (Pecan to 3rd) and Broadway & McCullough Intersection (1/2 block each direction)
August 2022 thru September 2022

July 2022 Road Closures

Broadway (3rd to McCullough) and McCullough

(N. Alamo to Avenue B) 6.13.22 to 7.29.22

Broadway (Brooklyn to E. Jones) 6.13.22 to 10.28.22

July 2022 Project Updates

  • Broadway (E. Jones Avenue to 9th Street): Roadway reconstruction. Street, curb, sidewalk and driveway approach excavation. CPS manhole installation at E. Jones intersection, and 10th Street intersection completed. CPS underground distribution installation. Storm drain pipe installation, and curb inlet installation at 10th Street intersection completed. Roadway grading.
  • Broadway (9th Street to Brooklyn): Roadway reconstruction. Street, curb, sidewalk and driveway approach excavation.
  • Broadway (Brooklyn to 6th Street): SAWS water main excavation, installation, and tie-in. SAWS water service excavation, and installation.
  • Broadway (6th Street to McCullough): Planning SAWS water main excavation, installation, and tie-in. Planning SAWS water service excavation, and installation.
  • Broadway (McCullough to 4th): Planning SAWS water main excavation, installation, and tie-in. Planning SAWS water service excavation, and installation.
  • Broadway (4th to 3rd): Planning SAWS water main excavation, installation, and tie-in. Planning SAWS water service excavation, and installation.
  • McCullough Avenue (N. Alamo Street to Avenue B): Planning CPS overhead utility to underground installation.
  • 10th Street (N. Alamo Street to Avenue B): CPS overhead utility to underground installation.
  • North Alamo Street (McCullough Avenue to Travis): Street maintenance and clean-up work.
  • Avenue B (McCullough Avenue to E. Jones): Forming new curbs, sidewalks, driveway approaches, and wheel chair ramps.
  • Throughout project: AT&T telecommunication line installation. Removed trash, and hauled away debris.

May 2022 Road Closures

Broadway (4th to Brooklyn) 5.25.22 to 6.13.22

Broadway (3rd to McCullough) and McCullough

(N. Alamo to Avenue B) 6.13.22 to 7.29.22

Broadway (Brooklyn to E. Jones) and

10th (N. Alamo to Avenue B) 5.25.22 to 6.13.22

Broadway (Brooklyn to E. Jones) 6.13.22 to 10.28.22

May 2022 Project Updates

  • Broadway (E. Jones Avenue to 9th Street): Roadway reconstruction. Street, curb, sidewalk and driveway approach excavation. CPS manhole installation at E. Jones intersection, and 10th Street intersection completed. CPS underground distribution installation. Storm drain pipe installation, and curb inlet installation at 10th Street intersection completed. Roadway grading.
  • Broadway (9th Street to Brooklyn): Roadway reconstruction. Street, curb, sidewalk and driveway approach excavation.
  • Broadway (Brooklyn to 6th Street): SAWS water main excavation, installation, and tie-in. SAWS water service excavation, and installation.
  • Broadway (6th Street to McCullough): Planning SAWS water main excavation, installation, and tie-in. Planning SAWS water service excavation, and installation.
  • Broadway (McCullough to 4th): Planning SAWS water main excavation, installation, and tie-in. Planning SAWS water service excavation, and installation.
  • Broadway (4th to 3rd): Planning SAWS water main excavation, installation, and tie-in. Planning SAWS water service excavation, and installation.
  • McCullough Avenue (N. Alamo Street to Avenue B): Planning CPS overhead utility to underground installation.
  • 10th Street (N. Alamo Street to Avenue B): CPS overhead utility to underground installation.
  • North Alamo Street (McCullough Avenue to Travis): Street maintenance and clean-up work.
  • Avenue B (McCullough Avenue to E. Jones): Forming new curbs, sidewalks, driveway approaches, and wheel chair ramps.
  • Throughout project: AT&T telecommunication line installation. Removed trash, and hauled away debris.

April 2022 Road Closures

  • Broadway (6th St. to E. Jones) and 8th St. (N. Alamo to Avenue B) and 9th St. (N. Alamo to Avenue B) and 10th St. (N. Alamo to Avenue B): 4.12.22 to 5.27.22

April 2022 Project Updates

  • Broadway (E. Jones Avenue to 9th Street): Roadway reconstruction. Street, curb, sidewalk and driveway approach excavation.
  • Broadway (9th Street to Brooklyn): SAWS water main excavation, installation, and tie-in completed. SAWS water service excavation, and installation completed. Trench restoration completed. Roadway reconstruction. Street, curb, sidewalk and driveway approach excavation.
  • Broadway (Brooklyn to 6th Street): SAWS water main excavation, installation, and tie-in. SAWS water service excavation, and installation.
  • 8th Street (N. Alamo Street to Avenue B): CPS overhead utility to underground installation.
  • 10th Street (N. Alamo Street to Avenue B): CPS overhead utility to underground installation.
  • North Alamo Street (McCullough Avenue to Travis): Street maintenance and clean-up work.
  • Avenue B (McCullough Avenue to 10th Street): Forming new curbs, sidewalks, driveway approaches, and wheel chair ramps.
  • Throughout project: AT&T telecommunication line installation. Removed trash, and hauled away debris.

March 2022 Road Closures

  • Broadway (Brooklyn to 9th St.) and 8th St. (N. Alamo to Avenue B): 3.10.22 to 4.11.22
  • Broadway (Brooklyn to E. Jones) and 8th St. (N. Alamo to Avenue B) and 9th St. (N. Alamo to Avenue B) and 10th St. (N. Alamo to Avenue B): 4.11.22 to 4.12.22
  • Broadway (6th St. to E. Jones) and 8th St. (N. Alamo to Avenue B) and 9th St. (N. Alamo to Avenue B) and 10th St. (N. Alamo to Avenue B): 4.12.22 to 5.27.22

March 2022 Construction Activities

  • Broadway (E. Jones Avenue to 9th Street): SAWS water service installation, and water main tie-in completed. Trench restoration completed.
  • Broadway (Brooklyn to 9th Street): SAWS water main excavation, installation, and tie-in. SAWS water service excavation, and installation. Trench restoration.
  • Broadway (6th Street to Brooklyn): Planning SAWS water main excavation, installation, and tie-in. Planning SAWS water service excavation, and installation.
  • 6th Street (N. Alamo Street to Avenue B): CPS overhead utility to underground installation completed.
  • 8th Street (N. Alamo Street to Avenue B): CPS overhead utility to underground installation.
  • Broadway (Pecan to 4th Street): Televised inspection of existing SAWS sewer main, prior to sewer lining installation.
  • North Alamo Street (McCullough Avenue to Travis): Street maintenance and clean-up work.
  • Avenue B (McCullough Avenue to 10th Street): Demolition of curbs, sidewalk, driveway approaches, and wheel chair ramps. Forming new curbs, sidewalks, driveway approaches, and wheel chair ramps.
  • Thru-out project: Removed trash, and hauled away debris.

February 2022 Road Closures

  • Broadway (E. Jones to 9th Street): 1.24.22 to 3.2.22
  • 6th Street (N. Alamo to Avenue B): 1.24.22 to 2.25.22
  • 8th Street (N. Alamo to Avenue B): 1.24.22 to 4.11.22
  • Broadway (10th Street to 8th Street): 3.2.22 to 3.9.22
  • Broadway (Brooklyn to 9th Street): 3.10.22 to 4.11.22

February 2022 Construction Activities

  • Broadway (E. Jones Avenue to 9th Street): SAWS water service excavation, and installation.
  • Broadway (Brooklyn to 9th Street): Planning SAWS water main excavation, and installation. Planning SAWS water service excavation, and installation.
  • 6th Street (N. Alamo Street to Avenue B): CPS overhead utility to underground installation.
  • 8th Street (N. Alamo Street to Avenue B): Planning CPS overhead utility to underground installation.
  • Broadway (Pecan to 4th Street): Televised inspection of existing SAWS sewer main, prior to sewer lining installation.
  • North Alamo Street (McCullough Avenue to Travis): Street maintenance and clean-up work.
  • Avenue B (McCullough Avenue to 10th Street): Demolition of curbs, and sidewalk. Forming new curbs, sidewalks, and wheel chair ramps.
  • Thru-out project: Preparing for placement of temporary roadway striping. Removed trash and hauled away debris.

January 2022 Road Closures

  • 6th Street (N. Alamo to Avenue B): 11.17.21 to 2.4.22
  • Broadway (E. Jones to 9th Street): 1.11.22 to 2.4.22
  • Broadway (Pecan to 3rd Street): 1.25.22 to 2.7.22
  • Brooklyn Avenue (N. Alamo to Avenue B): 1.25.22 to 3.7.22
  • Broadway (Brooklyn Avenue to 9th Street): 2.7.22 to 3.21.22

January 2022 Construction Activities

  • Broadway (E. Jones Avenue to 10th Street): SAWS water main excavation, and installation completed. SAWS water service excavation, and installation completed.
  • Broadway (9th Street to 10th Street): SAWS sewer manhole, sewer main excavation, and installation completed. SAWS sewer lateral excavation, and installation completed. SAWS water main excavation, and installation completed. SAWS water service excavation, and installation completed.
  • Broadway (Brooklyn to 9th Street): Planning SAWS water main excavation, and installation. Planning SAWS water service excavation, and installation.
  • Brooklyn Avenue (N. Alamo Street to Avenue B): Planning CPS overhead utility to underground installation.
  • 6th Street (N. Alamo Street to Avenue B): CPS overhead utility to underground installation.
  • Broadway (Pecan to 3rd Street): Planning SAWS permanent sewer lining installation inside existing sewer main.
  • North Alamo Street (McCullough Avenue to Travis): Miscellaneous concrete work to landscaping beds.
  • Avenue B (McCullough Avenue to 9th Street): Demolition of curbs, and sidewalk. Forming new curbs, sidewalks, and wheel chair ramps.
  • Removed trash and hauled away debris.

December 2021 Road Closures

  • Broadway & E. Jones (1/2 block north & south): 11.17.21 to 12.21.21
  • Broadway (9th Street to 10th Street): 11.17.21 to 12.21.21
  • 6th Street (N. Alamo to Avenue B): 11.17.21 to 1.27.22
  • Broadway (E. Jones to north of 10th Street): 12.21.21 to 1.3.22
  • Broadway (9th Street to 10th Street): 12.21.21 to 1.3.22
  • Broadway (E. Jones to 9th Street): 1.3.22 to 2.4.22
  • Brooklyn Avenue (N. Alamo to Avenue B): 1.10.22 to 2.28.22

December 2021 Construction Activities

  • Broadway (8th Street to 9th Street): SAWS sewer main, sewer lateral installation, and trench restoration completed.
  • Broadway (9th Street to 10th Street): SAWS manhole, sewer main excavation and installation.
  • Broadway (Roy Smith to E. Jones Avenue): SAWS water main, water services, and trench restoration completed.
  • Broadway (E. Jones Avenue to 10th Street): SAWS water main excavation and installation.
  • North Alamo Street (McCullough Avenue to Travis): Formed concrete island landscaping beds adjacent to bike lanes. Formed curb, sidewalk, and wheel chair ramp.
  • Removed trash and hauled away debris.

November 2021 Road Closures

  • Broadway & E. Jones (1/2 block north & south): 11.17.21 to 12.21.21
  • Broadway (9th Street to 10th Street): 11.17.21 to 12.21.21
  • 6th Street (N. Alamo to Avenue B): 11.17.21 to 1.10.22
  • Broadway (E. Jones to north of 10th Street): 12.21.21 to 1.3.22
  • Broadway (9th Street to 10th Street): 12.21.21 to 1.3.22
  • Broadway (E. Jones to 9th Street): 12.21.21 to 1.3.22

November 2012 Construction Activities

  • Broadway (8th Street to 9th Street): SAWS sewer main, sewer lateral installation, and trench restoration completed.
  • Broadway (9th Street to 10th Street): SAWS manhole, sewer main excavation and installation.
  • Broadway (Roy Smith to E. Jones Avenue): SAWS water main, water services, and trench restoration completed.
  • Broadway (E. Jones Avenue to 10th Street): SAWS water main excavation and installation.
  • North Alamo Street (McCullough Avenue to Travis): Formed concrete island landscaping beds adjacent to bike lanes. Formed curb, sidewalk, and wheel chair ramp.
  • Removed trash and hauled away debris.

October 2021 Construction Activities

  • Broadway (Brooklyn Avenue to 6th Street): SAWS sewer manhole work, and trench restoration at Broadway & 6th Street completed. SAWS sewer lateral installation, and trench restoration completed.
  • Broadway (6th Street to McCullough Avenue): SAWS sewer lateral trench restoration completed.
  • Broadway (Brooklyn Avenue to 8th Street): SAWS sewer main installation, and trench restoration completed. SAWS sewer lateral installation, and trench restoration completed.
  • Broadway (8th Street to 9th Street): SAWS sewer main excavation and installation. SAWS sewer lateral excavation and installation.
  • Broadway (Roy Smith to E. Jones): SAWS water main excavation, and installation completed. SAWS water service excavation, installation and tie-in completed.
  • North Alamo (McCullough Avenue to Travis): Forming concrete island landscaping beds adjacent to bike lanes. Formed curb, sidewalk, and wheel chair ramp.
  • Removed trash and hauled away debris.

September 2021 Construction Activities

  • Broadway (Brooklyn Avenue to 6th Street): SAWS sewer main excavation and installation completed. SAWS sewer manhole work at Broadway & 6th Street. SAWS sewer lateral excavation and installation.
  • Broadway (6th Street to McCullough Avenue): AT&T trench restoration completed. SAWS sewer main trench restoration completed. SAWS sewer lateral trench restoration. SAWS sewer manhole trench restoration at Broadway & McCullough completed.
  • Broadway (McCullough Avenue to 4th Street): AT&T utility duct bank trench restoration completed. CPS utility duct bank trench restoration completed. SAWS sewer manhole trench restoration at Broadway & 4th Street completed.
  • Broadway (4th Street to 3rd Street): AT&T manhole, utility duct bank installation and trench restoration completed. CPS utility duct bank installation and trench restoration completed.
  • Broadway (3rd Street to Pecan Street): AT&T manhole, utility duct bank installation and trench restoration completed. CPS utility duct bank installation and trench restoration completed.
  • Broadway (Pecan Street to Travis Street): AT&T manhole, utility duct bank installation and trench restoration completed. CPS utility duct bank installation and trench restoration completed.
  • Broadway (Brooklyn Avenue to 8th Street): Planning SAWS sewer main excavation and installation. Planning SAWS sewer lateral excavation and installation.
  • Broadway (8th Street to 9th Street): Planning SAWS sewer main excavation and installation. Planning SAWS sewer lateral excavation and installation.
  • Broadway (Roy Smith to 12th Street): SAWS water main excavation and installation.
  • North Alamo Street (McCullough Avenue to Travis): Street asphalt work completed. Crews starting to form concrete island landscaping beds adjacent to bike lanes.
  • Removed trash and hauled away debris.

August 2021 Construction Activities

  • Broadway (Brooklyn Avenue to 6th Street): SAWS sewer main excavation and installation. SAWS sewer manhole installation at Broadway & 6th Street.
  • Broadway (6th Street to McCullough Avenue): AT&T trench restoration. SAWS sewer main trench restoration. SAWS sewer lateral excavation and installation completed, trench restoration. SAWS sewer manhole trench restoration at Broadway & McCullough.
  • Broadway (McCullough Avenue to 4th Street): AT&T utility duct bank trench restoration. CPS utility duct bank trench restoration. SAWS sewer manhole trench restoration at Broadway & 4th Street.
  • Broadway (4th Street to 3rd Street): AT&T manhole, and utility duct bank installation and trench restoration. CPS utility duct bank installation and trench restoration. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (3rd Street to Pecan Street): AT&T manhole, and utility duct bank excavation and installation. CPS utility duct bank excavation and installation. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (Pecan Street to Travis Street): AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation.
  • Broadway (Brooklyn Avenue to 8th Street): Planning SAWS sewer main excavation and installation. Planning SAWS sewer lateral excavation and installation.
  • Broadway (8th Street to 9th Street): Planning SAWS sewer main excavation and installation. Planning SAWS sewer lateral excavation and installation.
  • Removed trash and hauled away the debris.

July 2021 Construction Activities

  • Broadway (Brooklyn Avenue to 6th Street): SAWS sewer main excavation and installation. SAWS sewer manhole installation at Broadway & 6th Street.
  • Broadway (6th Street to McCullough Avenue): AT&T trench restoration. SAWS sewer main trench restoration. SAWS sewer lateral excavation and installation completed, trench restoration. SAWS sewer manhole trench restoration at Broadway & McCullough.
  • Broadway (McCullough Avenue to 4th Street): AT&T utility duct bank trench restoration. CPS utility duct bank trench restoration. SAWS sewer manhole trench restoration at Broadway & 4th Street.
  • Broadway (4th Street to 3rd Street): AT&T manhole, and utility duct bank installation and trench restoration. CPS utility duct bank installation and trench restoration. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (3rd Street to Pecan Street): AT&T manhole, and utility duct bank excavation and installation. CPS utility duct bank excavation and installation. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (Pecan Street to Travis Street): AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation.
  • Broadway (Brooklyn Avenue to 8th Street): Planning SAWS sewer main excavation and installation. Planning SAWS sewer lateral excavation and installation.
  • Broadway (8th Street to 9th Street): Planning SAWS sewer main excavation and installation. Planning SAWS sewer lateral excavation and installation.
  • Removed trash and hauled away the debris.

June 2021 Construction Activities

The contractor continues installation of AT&T duct bank work through the Broadway corridor, which is associated with the $42 Million, 2017 Bond Project. Businesses and residents have sidewalk and parking lot accessibility.

Construction began on July 2020 and will be substantially complete by December 2023. For ease of reference, a map of the closures and detour routes is provided below.

  • Broadway (Brooklyn Avenue to 6th Street): AT&T & CPS trench restoration completed. SAWS sewer main excavation.
  • Broadway (6th Street to McCullough Avenue): AT&T & CPS trench restoration. SAWS sewer main completed. SAWS sewer lateral excavation and installation. SAWS sewer manhole installation at Broadway & McCullough.
  • Broadway (McCullough Avenue to 4th Street): AT&T utility duct bank restoration. CPS utility duct bank excavation, installation and trench restoration. SAWS sewer main completed. SAWS sewer laterals completed. SAWS sewer manhole installation at Broadway & 4th Street.
  • Broadway (4th Street to 3rd Street): AT&T manhole, and utility duct bank excavation and installation. CPS utility duct bank excavation and installation. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (3rd Street to Pecan Street): AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (Pecan Street to Travis Street): Preparations for AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation.
  • Removed trash and hauled away debris.

May 2021 Construction Activities

  • Broadway (Brooklyn Avenue to 6th Street): AT&T & CPS trench restoration. SAWS sewer main excavation.
  • Broadway (6th Street to McCullough Avenue): AT&T utility duct bank completed. CPS utility duct bank completed. AT&T & CPS trench restoration. SAWS sewer main completed. SAWS sewer lateral excavation and installation.
  • Broadway (McCullough Avenue to 4th Street): AT&T utility duct bank completed. CPS utility duct bank excavation and installation. SAWS sewer main completed. SAWS sewer laterals completed. SAWS sewer manhole installation at Broadway & 4th Street intersection.
  • Broadway (4th Street to 3rd Street): AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation. SAWS sewer manhole removal at Broadway & 3rd Street intersection. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (3rd Street to Pecan Street): Preparations for AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (Pecan Street to Travis Street): SAWS sewer manhole work at Broadway & Pecan intersection. Preparations for AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation.
  • Removed trash and hauled away debris.

Road Closures

Brooklyn Avenue to 4th Street:

March 4, 2021 thru April 26, 2021

 

Brooklyn Avenue to Pecan Street:

April 26, 2021 thru May 17, 2021

The contractor continues installation of AT&T duct bank work through the Broadway corridor, which is associated with the $42 Million, 2017 Bond Project. Businesses and residents have sidewalk and parking lot accessibility.

 

Broadway Road Closure

Brooklyn Avenue to 4th Street

3.4.21 thru 4.26.21

Click here for a larger map

Construction began on July 2020 and will be substantially complete by December 2023. For ease of reference a map of the closures and detour routes is provided below.

 

Broadway Road Closure

Brooklyn Avenue to Pecan Street

4.26.21 thru 5.17.21

Click here for a larger map

Updates for March 2021

The contractor continues installation of AT&T duct bank work through the Broadway corridor, which is associated with the $42 Million, 2017 Bond Project. Businesses and residents have sidewalk and parking lot accessibility. 

Construction began on July 2020 and will be substantially complete by December 2023. For ease of reference a map of the closures and detour routes is provided below. 

Thank you for your patience as we improve your community!

*ALL WORK IS SUBJECT TO FAVORABLE WEATHER CONDITIONS

If you have questions about the project, please contact:

Joey Doctor
Capital Projects Officer
Public Works Department (PWD)
(210) 207-8415 or joe.doctor@sanantonio.gov 