CONSTRUCTION UPDATES

Road closures and alternate routes are made monthly.
Check here for the most up-to-date information and join our email list for regular updates.

Broadway Road Closure Construction Map

6th Street (N. Alamo to Avenue B):
11.17.21 to 1.27.22

Click here for a Street View map

Broadway Road Closure Construction Map

Broadway (E. Jones to 9th Street):
1.3.22 to 2.4.22

Click here for a Street View map

Broadway Road Closure Construction Map

Brooklyn Avenue (N. Alamo to Avenue B):
1.10.22 to 2.28.22

Click here for a Street View map

Project Notes

The contractor continues installation of SAWS sewer and water through the Broadway corridor, and CPS overhead to underground work. This work is associated with the $42 Million, 2017 Bond Project. Businesses and residents have sidewalk and parking lot accessibility. Bike lane work continues on Avenue B (McCullough to 9th Street), this is in association with the Avenue B/North Alamo bike lanes. Access to local traffic and businesses will be maintained.

Public Works Department will continue to communicate any changes or updates to Council District 1 & 2 and Council District staff, surrounding businesses and residents as well on all social media platforms.

Construction began on July 2020 and will be substantially complete by December 2023. For ease of reference a list of road closures and detour route maps is provided.

December 2021 Road Closures

  • Broadway & E. Jones (1/2 block north & south): 11.17.21 to 12.21.21
  • Broadway (9th Street to 10th Street): 11.17.21 to 12.21.21
  • 6th Street (N. Alamo to Avenue B): 11.17.21 to 1.27.22
  • Broadway (E. Jones to north of 10th Street): 12.21.21 to 1.3.22
  • Broadway (9th Street to 10th Street): 12.21.21 to 1.3.22
  • Broadway (E. Jones to 9th Street): 1.3.22 to 2.4.22
  • Brooklyn Avenue (N. Alamo to Avenue B): 1.10.22 to 2.28.22

December 2012 Construction Activities

  • Broadway (8th Street to 9th Street): SAWS sewer main, sewer lateral installation, and trench restoration completed.
  • Broadway (9th Street to 10th Street): SAWS manhole, sewer main excavation and installation.
  • Broadway (Roy Smith to E. Jones Avenue): SAWS water main, water services, and trench restoration completed.
  • Broadway (E. Jones Avenue to 10th Street): SAWS water main excavation and installation.
  • North Alamo Street (McCullough Avenue to Travis): Formed concrete island landscaping beds adjacent to bike lanes. Formed curb, sidewalk, and wheel chair ramp.
  • Removed trash and hauled away debris.

November 2021 Road Closures

  • Broadway & E. Jones (1/2 block north & south): 11.17.21 to 12.21.21
  • Broadway (9th Street to 10th Street): 11.17.21 to 12.21.21
  • 6th Street (N. Alamo to Avenue B): 11.17.21 to 1.10.22
  • Broadway (E. Jones to north of 10th Street): 12.21.21 to 1.3.22
  • Broadway (9th Street to 10th Street): 12.21.21 to 1.3.22
  • Broadway (E. Jones to 9th Street): 12.21.21 to 1.3.22

November 2012 Construction Activities

  • Broadway (8th Street to 9th Street): SAWS sewer main, sewer lateral installation, and trench restoration completed.
  • Broadway (9th Street to 10th Street): SAWS manhole, sewer main excavation and installation.
  • Broadway (Roy Smith to E. Jones Avenue): SAWS water main, water services, and trench restoration completed.
  • Broadway (E. Jones Avenue to 10th Street): SAWS water main excavation and installation.
  • North Alamo Street (McCullough Avenue to Travis): Formed concrete island landscaping beds adjacent to bike lanes. Formed curb, sidewalk, and wheel chair ramp.
  • Removed trash and hauled away debris.

October 2021 Construction Activities

  • Broadway (Brooklyn Avenue to 6th Street): SAWS sewer manhole work, and trench restoration at Broadway & 6th Street completed. SAWS sewer lateral installation, and trench restoration completed.
  • Broadway (6th Street to McCullough Avenue): SAWS sewer lateral trench restoration completed.
  • Broadway (Brooklyn Avenue to 8th Street): SAWS sewer main installation, and trench restoration completed. SAWS sewer lateral installation, and trench restoration completed.
  • Broadway (8th Street to 9th Street): SAWS sewer main excavation and installation. SAWS sewer lateral excavation and installation.
  • Broadway (Roy Smith to E. Jones): SAWS water main excavation, and installation completed. SAWS water service excavation, installation and tie-in completed.
  • North Alamo (McCullough Avenue to Travis): Forming concrete island landscaping beds adjacent to bike lanes. Formed curb, sidewalk, and wheel chair ramp.
  • Removed trash and hauled away debris.

September 2021 Construction Activities

  • Broadway (Brooklyn Avenue to 6th Street): SAWS sewer main excavation and installation completed. SAWS sewer manhole work at Broadway & 6th Street. SAWS sewer lateral excavation and installation.
  • Broadway (6th Street to McCullough Avenue): AT&T trench restoration completed. SAWS sewer main trench restoration completed. SAWS sewer lateral trench restoration. SAWS sewer manhole trench restoration at Broadway & McCullough completed.
  • Broadway (McCullough Avenue to 4th Street): AT&T utility duct bank trench restoration completed. CPS utility duct bank trench restoration completed. SAWS sewer manhole trench restoration at Broadway & 4th Street completed.
  • Broadway (4th Street to 3rd Street): AT&T manhole, utility duct bank installation and trench restoration completed. CPS utility duct bank installation and trench restoration completed.
  • Broadway (3rd Street to Pecan Street): AT&T manhole, utility duct bank installation and trench restoration completed. CPS utility duct bank installation and trench restoration completed.
  • Broadway (Pecan Street to Travis Street): AT&T manhole, utility duct bank installation and trench restoration completed. CPS utility duct bank installation and trench restoration completed.
  • Broadway (Brooklyn Avenue to 8th Street): Planning SAWS sewer main excavation and installation. Planning SAWS sewer lateral excavation and installation.
  • Broadway (8th Street to 9th Street): Planning SAWS sewer main excavation and installation. Planning SAWS sewer lateral excavation and installation.
  • Broadway (Roy Smith to 12th Street): SAWS water main excavation and installation.
  • North Alamo Street (McCullough Avenue to Travis): Street asphalt work completed. Crews starting to form concrete island landscaping beds adjacent to bike lanes.
  • Removed trash and hauled away debris.

August 2021 Construction Activities

  • Broadway (Brooklyn Avenue to 6th Street): SAWS sewer main excavation and installation. SAWS sewer manhole installation at Broadway & 6th Street.
  • Broadway (6th Street to McCullough Avenue): AT&T trench restoration. SAWS sewer main trench restoration. SAWS sewer lateral excavation and installation completed, trench restoration. SAWS sewer manhole trench restoration at Broadway & McCullough.
  • Broadway (McCullough Avenue to 4th Street): AT&T utility duct bank trench restoration. CPS utility duct bank trench restoration. SAWS sewer manhole trench restoration at Broadway & 4th Street.
  • Broadway (4th Street to 3rd Street): AT&T manhole, and utility duct bank installation and trench restoration. CPS utility duct bank installation and trench restoration. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (3rd Street to Pecan Street): AT&T manhole, and utility duct bank excavation and installation. CPS utility duct bank excavation and installation. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (Pecan Street to Travis Street): AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation.
  • Broadway (Brooklyn Avenue to 8th Street): Planning SAWS sewer main excavation and installation. Planning SAWS sewer lateral excavation and installation.
  • Broadway (8th Street to 9th Street): Planning SAWS sewer main excavation and installation. Planning SAWS sewer lateral excavation and installation.
  • Removed trash and hauled away the debris.

July 2021 Construction Activities

  • Broadway (Brooklyn Avenue to 6th Street): SAWS sewer main excavation and installation. SAWS sewer manhole installation at Broadway & 6th Street.
  • Broadway (6th Street to McCullough Avenue): AT&T trench restoration. SAWS sewer main trench restoration. SAWS sewer lateral excavation and installation completed, trench restoration. SAWS sewer manhole trench restoration at Broadway & McCullough.
  • Broadway (McCullough Avenue to 4th Street): AT&T utility duct bank trench restoration. CPS utility duct bank trench restoration. SAWS sewer manhole trench restoration at Broadway & 4th Street.
  • Broadway (4th Street to 3rd Street): AT&T manhole, and utility duct bank installation and trench restoration. CPS utility duct bank installation and trench restoration. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (3rd Street to Pecan Street): AT&T manhole, and utility duct bank excavation and installation. CPS utility duct bank excavation and installation. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (Pecan Street to Travis Street): AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation.
  • Broadway (Brooklyn Avenue to 8th Street): Planning SAWS sewer main excavation and installation. Planning SAWS sewer lateral excavation and installation.
  • Broadway (8th Street to 9th Street): Planning SAWS sewer main excavation and installation. Planning SAWS sewer lateral excavation and installation.
  • Removed trash and hauled away the debris.

June 2021 Construction Activities

The contractor continues installation of AT&T duct bank work through the Broadway corridor, which is associated with the $42 Million, 2017 Bond Project. Businesses and residents have sidewalk and parking lot accessibility.

Construction began on July 2020 and will be substantially complete by December 2023. For ease of reference, a map of the closures and detour routes is provided below.

  • Broadway (Brooklyn Avenue to 6th Street): AT&T & CPS trench restoration completed. SAWS sewer main excavation.
  • Broadway (6th Street to McCullough Avenue): AT&T & CPS trench restoration. SAWS sewer main completed. SAWS sewer lateral excavation and installation. SAWS sewer manhole installation at Broadway & McCullough.
  • Broadway (McCullough Avenue to 4th Street): AT&T utility duct bank restoration. CPS utility duct bank excavation, installation and trench restoration. SAWS sewer main completed. SAWS sewer laterals completed. SAWS sewer manhole installation at Broadway & 4th Street.
  • Broadway (4th Street to 3rd Street): AT&T manhole, and utility duct bank excavation and installation. CPS utility duct bank excavation and installation. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (3rd Street to Pecan Street): AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (Pecan Street to Travis Street): Preparations for AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation.
  • Removed trash and hauled away debris.

May 2021 Construction Activities

  • Broadway (Brooklyn Avenue to 6th Street): AT&T & CPS trench restoration. SAWS sewer main excavation.
  • Broadway (6th Street to McCullough Avenue): AT&T utility duct bank completed. CPS utility duct bank completed. AT&T & CPS trench restoration. SAWS sewer main completed. SAWS sewer lateral excavation and installation.
  • Broadway (McCullough Avenue to 4th Street): AT&T utility duct bank completed. CPS utility duct bank excavation and installation. SAWS sewer main completed. SAWS sewer laterals completed. SAWS sewer manhole installation at Broadway & 4th Street intersection.
  • Broadway (4th Street to 3rd Street): AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation. SAWS sewer manhole removal at Broadway & 3rd Street intersection. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (3rd Street to Pecan Street): Preparations for AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (Pecan Street to Travis Street): SAWS sewer manhole work at Broadway & Pecan intersection. Preparations for AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation.
  • Removed trash and hauled away debris.

Road Closures

Brooklyn Avenue to 4th Street:

March 4, 2021 thru April 26, 2021

 

Brooklyn Avenue to Pecan Street:

April 26, 2021 thru May 17, 2021

The contractor continues installation of AT&T duct bank work through the Broadway corridor, which is associated with the $42 Million, 2017 Bond Project. Businesses and residents have sidewalk and parking lot accessibility.

 

Broadway Road Closure

Brooklyn Avenue to 4th Street

3.4.21 thru 4.26.21

Click here for a larger map

Construction began on July 2020 and will be substantially complete by December 2023. For ease of reference a map of the closures and detour routes is provided below.

 

Broadway Road Closure

Brooklyn Avenue to Pecan Street

4.26.21 thru 5.17.21

Click here for a larger map

Updates for March 2021

The contractor continues installation of AT&T duct bank work through the Broadway corridor, which is associated with the $42 Million, 2017 Bond Project. Businesses and residents have sidewalk and parking lot accessibility. 

Construction began on July 2020 and will be substantially complete by December 2023. For ease of reference a map of the closures and detour routes is provided below. 

Planned activities for the next 4+ weeks:

The contractor continues installation of AT&T duct bank work, SAWS sewer, and CPS network construction through the Broadway corridor, which is associated with the $42 Million, 2017 Bond Project. Businesses and residents have sidewalk and parking lot accessibility.

Construction began on July 2020 and will be substantially complete by December 2023. For ease of reference, a map of the closures and detour routes is provided below.

Activity Estimated Date*

Broadway (9th Street to 10th Street): Continue SAWS sewer manhole installation. Continue SAWS sewer main excavation and installation. Continue SAWS sewer lateral excavation and installation.

December 2021

Broadway (E. Jones Avenue to 10th street): Continue SAWS water main excavation and installation. Continue SAWS water service excavation, and installation.

December 2021

North Alamo Street (McCullough Avenue to Travis): Continue miscellaneous concrete work to landscaping beds. Clean up street.

December 2021

6th Street (N. Alamo Street to Avenue B): Continue CPS overhead utility to underground installation.

December 2021

Avenue B (McCullough Avenue to 9th Street): Continue demolition of curbs and sidewalk. Start forming new curb, and sidewalks.

December 2021

Brooklyn Avenue (N. Alamo Street to Avenue B): Begin CPS overhead utility to underground installation.

December 2021

Remove trash and haul away debris.

December 2021

Thank you for your patience as we improve your community!

*ALL WORK IS SUBJECT TO FAVORABLE WEATHER CONDITIONS

If you have questions about the project, please contact:

Joey Doctor
Capital Projects Officer
Public Works Department (PWD)
(210) 207-8415 or joe.doctor@sanantonio.gov 

After working hours or weekends, please call 311 or (210) 207-6000