CONSTRUCTION UPDATES

Road closures and alternate routes are made monthly.
Check here for the most up-to-date information and join our email list for regular updates.

Broadway Road Closure Construction Map

Broadway (6th St. to E. Jones) and 8th St. (N. Alamo to Avenue B) and 9th St. (N. Alamo to Avenue B) and 10th St. (N. Alamo to Avenue B):

4.12.22 to 5.27.22

Click here for a Street View map

Project Notes

The contractor continues installation of SAWS water through the Broadway corridor, CPS overhead to underground work, and roadway reconstruction. This work is associated with the $42 Million, 2017 Bond Project. Businesses and residents have sidewalk and parking lot accessibility. Bike lane work continues on Avenue B (McCullough to 10th Street), this is in association with the Avenue B/North Alamo bike lanes. Access to local traffic and businesses will be maintained.

Public Works Department will continue to communicate any changes or updates to Council District 1 & 2 and Council District staff, surrounding businesses and residents as well on all social media platforms.

Construction began on July 2020 and will be substantially complete by December 2023. For ease of reference a list of road closures and detour route map is provided.

April 2022 Road Closures

  • Broadway (6th St. to E. Jones) and 8th St. (N. Alamo to Avenue B) and 9th St. (N. Alamo to Avenue B) and 10th St. (N. Alamo to Avenue B): 4.12.22 to 5.27.22

April 2022 Project Updates

  • Broadway (E. Jones Avenue to 9th Street): Roadway reconstruction. Street, curb, sidewalk and driveway approach excavation.
  • Broadway (9th Street to Brooklyn): SAWS water main excavation, installation, and tie-in completed. SAWS water service excavation, and installation completed. Trench restoration completed. Roadway reconstruction. Street, curb, sidewalk and driveway approach excavation.
  • Broadway (Brooklyn to 6th Street): SAWS water main excavation, installation, and tie-in. SAWS water service excavation, and installation.
  • 8th Street (N. Alamo Street to Avenue B): CPS overhead utility to underground installation.
  • 10th Street (N. Alamo Street to Avenue B): CPS overhead utility to underground installation.
  • North Alamo Street (McCullough Avenue to Travis): Street maintenance and clean-up work.
  • Avenue B (McCullough Avenue to 10th Street): Forming new curbs, sidewalks, driveway approaches, and wheel chair ramps.
  • Throughout project: AT&T telecommunication line installation. Removed trash, and hauled away debris.

March 2022 Road Closures

  • Broadway (Brooklyn to 9th St.) and 8th St. (N. Alamo to Avenue B): 3.10.22 to 4.11.22
  • Broadway (Brooklyn to E. Jones) and 8th St. (N. Alamo to Avenue B) and 9th St. (N. Alamo to Avenue B) and 10th St. (N. Alamo to Avenue B): 4.11.22 to 4.12.22
  • Broadway (6th St. to E. Jones) and 8th St. (N. Alamo to Avenue B) and 9th St. (N. Alamo to Avenue B) and 10th St. (N. Alamo to Avenue B): 4.12.22 to 5.27.22

March 2022 Construction Activities

  • Broadway (E. Jones Avenue to 9th Street): SAWS water service installation, and water main tie-in completed. Trench restoration completed.
  • Broadway (Brooklyn to 9th Street): SAWS water main excavation, installation, and tie-in. SAWS water service excavation, and installation. Trench restoration.
  • Broadway (6th Street to Brooklyn): Planning SAWS water main excavation, installation, and tie-in. Planning SAWS water service excavation, and installation.
  • 6th Street (N. Alamo Street to Avenue B): CPS overhead utility to underground installation completed.
  • 8th Street (N. Alamo Street to Avenue B): CPS overhead utility to underground installation.
  • Broadway (Pecan to 4th Street): Televised inspection of existing SAWS sewer main, prior to sewer lining installation.
  • North Alamo Street (McCullough Avenue to Travis): Street maintenance and clean-up work.
  • Avenue B (McCullough Avenue to 10th Street): Demolition of curbs, sidewalk, driveway approaches, and wheel chair ramps. Forming new curbs, sidewalks, driveway approaches, and wheel chair ramps.
  • Thru-out project: Removed trash, and hauled away debris.

February 2022 Road Closures

  • Broadway (E. Jones to 9th Street): 1.24.22 to 3.2.22
  • 6th Street (N. Alamo to Avenue B): 1.24.22 to 2.25.22
  • 8th Street (N. Alamo to Avenue B): 1.24.22 to 4.11.22
  • Broadway (10th Street to 8th Street): 3.2.22 to 3.9.22
  • Broadway (Brooklyn to 9th Street): 3.10.22 to 4.11.22

February 2022 Construction Activities

  • Broadway (E. Jones Avenue to 9th Street): SAWS water service excavation, and installation.
  • Broadway (Brooklyn to 9th Street): Planning SAWS water main excavation, and installation. Planning SAWS water service excavation, and installation.
  • 6th Street (N. Alamo Street to Avenue B): CPS overhead utility to underground installation.
  • 8th Street (N. Alamo Street to Avenue B): Planning CPS overhead utility to underground installation.
  • Broadway (Pecan to 4th Street): Televised inspection of existing SAWS sewer main, prior to sewer lining installation.
  • North Alamo Street (McCullough Avenue to Travis): Street maintenance and clean-up work.
  • Avenue B (McCullough Avenue to 10th Street): Demolition of curbs, and sidewalk. Forming new curbs, sidewalks, and wheel chair ramps.
  • Thru-out project: Preparing for placement of temporary roadway striping. Removed trash and hauled away debris.

January 2022 Road Closures

  • 6th Street (N. Alamo to Avenue B): 11.17.21 to 2.4.22
  • Broadway (E. Jones to 9th Street): 1.11.22 to 2.4.22
  • Broadway (Pecan to 3rd Street): 1.25.22 to 2.7.22
  • Brooklyn Avenue (N. Alamo to Avenue B): 1.25.22 to 3.7.22
  • Broadway (Brooklyn Avenue to 9th Street): 2.7.22 to 3.21.22

January 2022 Construction Activities

  • Broadway (E. Jones Avenue to 10th Street): SAWS water main excavation, and installation completed. SAWS water service excavation, and installation completed.
  • Broadway (9th Street to 10th Street): SAWS sewer manhole, sewer main excavation, and installation completed. SAWS sewer lateral excavation, and installation completed. SAWS water main excavation, and installation completed. SAWS water service excavation, and installation completed.
  • Broadway (Brooklyn to 9th Street): Planning SAWS water main excavation, and installation. Planning SAWS water service excavation, and installation.
  • Brooklyn Avenue (N. Alamo Street to Avenue B): Planning CPS overhead utility to underground installation.
  • 6th Street (N. Alamo Street to Avenue B): CPS overhead utility to underground installation.
  • Broadway (Pecan to 3rd Street): Planning SAWS permanent sewer lining installation inside existing sewer main.
  • North Alamo Street (McCullough Avenue to Travis): Miscellaneous concrete work to landscaping beds.
  • Avenue B (McCullough Avenue to 9th Street): Demolition of curbs, and sidewalk. Forming new curbs, sidewalks, and wheel chair ramps.
  • Removed trash and hauled away debris.

December 2021 Road Closures

  • Broadway & E. Jones (1/2 block north & south): 11.17.21 to 12.21.21
  • Broadway (9th Street to 10th Street): 11.17.21 to 12.21.21
  • 6th Street (N. Alamo to Avenue B): 11.17.21 to 1.27.22
  • Broadway (E. Jones to north of 10th Street): 12.21.21 to 1.3.22
  • Broadway (9th Street to 10th Street): 12.21.21 to 1.3.22
  • Broadway (E. Jones to 9th Street): 1.3.22 to 2.4.22
  • Brooklyn Avenue (N. Alamo to Avenue B): 1.10.22 to 2.28.22

December 2021 Construction Activities

  • Broadway (8th Street to 9th Street): SAWS sewer main, sewer lateral installation, and trench restoration completed.
  • Broadway (9th Street to 10th Street): SAWS manhole, sewer main excavation and installation.
  • Broadway (Roy Smith to E. Jones Avenue): SAWS water main, water services, and trench restoration completed.
  • Broadway (E. Jones Avenue to 10th Street): SAWS water main excavation and installation.
  • North Alamo Street (McCullough Avenue to Travis): Formed concrete island landscaping beds adjacent to bike lanes. Formed curb, sidewalk, and wheel chair ramp.
  • Removed trash and hauled away debris.

November 2021 Road Closures

  • Broadway & E. Jones (1/2 block north & south): 11.17.21 to 12.21.21
  • Broadway (9th Street to 10th Street): 11.17.21 to 12.21.21
  • 6th Street (N. Alamo to Avenue B): 11.17.21 to 1.10.22
  • Broadway (E. Jones to north of 10th Street): 12.21.21 to 1.3.22
  • Broadway (9th Street to 10th Street): 12.21.21 to 1.3.22
  • Broadway (E. Jones to 9th Street): 12.21.21 to 1.3.22

November 2012 Construction Activities

  • Broadway (8th Street to 9th Street): SAWS sewer main, sewer lateral installation, and trench restoration completed.
  • Broadway (9th Street to 10th Street): SAWS manhole, sewer main excavation and installation.
  • Broadway (Roy Smith to E. Jones Avenue): SAWS water main, water services, and trench restoration completed.
  • Broadway (E. Jones Avenue to 10th Street): SAWS water main excavation and installation.
  • North Alamo Street (McCullough Avenue to Travis): Formed concrete island landscaping beds adjacent to bike lanes. Formed curb, sidewalk, and wheel chair ramp.
  • Removed trash and hauled away debris.

October 2021 Construction Activities

  • Broadway (Brooklyn Avenue to 6th Street): SAWS sewer manhole work, and trench restoration at Broadway & 6th Street completed. SAWS sewer lateral installation, and trench restoration completed.
  • Broadway (6th Street to McCullough Avenue): SAWS sewer lateral trench restoration completed.
  • Broadway (Brooklyn Avenue to 8th Street): SAWS sewer main installation, and trench restoration completed. SAWS sewer lateral installation, and trench restoration completed.
  • Broadway (8th Street to 9th Street): SAWS sewer main excavation and installation. SAWS sewer lateral excavation and installation.
  • Broadway (Roy Smith to E. Jones): SAWS water main excavation, and installation completed. SAWS water service excavation, installation and tie-in completed.
  • North Alamo (McCullough Avenue to Travis): Forming concrete island landscaping beds adjacent to bike lanes. Formed curb, sidewalk, and wheel chair ramp.
  • Removed trash and hauled away debris.

September 2021 Construction Activities

  • Broadway (Brooklyn Avenue to 6th Street): SAWS sewer main excavation and installation completed. SAWS sewer manhole work at Broadway & 6th Street. SAWS sewer lateral excavation and installation.
  • Broadway (6th Street to McCullough Avenue): AT&T trench restoration completed. SAWS sewer main trench restoration completed. SAWS sewer lateral trench restoration. SAWS sewer manhole trench restoration at Broadway & McCullough completed.
  • Broadway (McCullough Avenue to 4th Street): AT&T utility duct bank trench restoration completed. CPS utility duct bank trench restoration completed. SAWS sewer manhole trench restoration at Broadway & 4th Street completed.
  • Broadway (4th Street to 3rd Street): AT&T manhole, utility duct bank installation and trench restoration completed. CPS utility duct bank installation and trench restoration completed.
  • Broadway (3rd Street to Pecan Street): AT&T manhole, utility duct bank installation and trench restoration completed. CPS utility duct bank installation and trench restoration completed.
  • Broadway (Pecan Street to Travis Street): AT&T manhole, utility duct bank installation and trench restoration completed. CPS utility duct bank installation and trench restoration completed.
  • Broadway (Brooklyn Avenue to 8th Street): Planning SAWS sewer main excavation and installation. Planning SAWS sewer lateral excavation and installation.
  • Broadway (8th Street to 9th Street): Planning SAWS sewer main excavation and installation. Planning SAWS sewer lateral excavation and installation.
  • Broadway (Roy Smith to 12th Street): SAWS water main excavation and installation.
  • North Alamo Street (McCullough Avenue to Travis): Street asphalt work completed. Crews starting to form concrete island landscaping beds adjacent to bike lanes.
  • Removed trash and hauled away debris.

August 2021 Construction Activities

  • Broadway (Brooklyn Avenue to 6th Street): SAWS sewer main excavation and installation. SAWS sewer manhole installation at Broadway & 6th Street.
  • Broadway (6th Street to McCullough Avenue): AT&T trench restoration. SAWS sewer main trench restoration. SAWS sewer lateral excavation and installation completed, trench restoration. SAWS sewer manhole trench restoration at Broadway & McCullough.
  • Broadway (McCullough Avenue to 4th Street): AT&T utility duct bank trench restoration. CPS utility duct bank trench restoration. SAWS sewer manhole trench restoration at Broadway & 4th Street.
  • Broadway (4th Street to 3rd Street): AT&T manhole, and utility duct bank installation and trench restoration. CPS utility duct bank installation and trench restoration. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (3rd Street to Pecan Street): AT&T manhole, and utility duct bank excavation and installation. CPS utility duct bank excavation and installation. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (Pecan Street to Travis Street): AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation.
  • Broadway (Brooklyn Avenue to 8th Street): Planning SAWS sewer main excavation and installation. Planning SAWS sewer lateral excavation and installation.
  • Broadway (8th Street to 9th Street): Planning SAWS sewer main excavation and installation. Planning SAWS sewer lateral excavation and installation.
  • Removed trash and hauled away the debris.

July 2021 Construction Activities

  • Broadway (Brooklyn Avenue to 6th Street): SAWS sewer main excavation and installation. SAWS sewer manhole installation at Broadway & 6th Street.
  • Broadway (6th Street to McCullough Avenue): AT&T trench restoration. SAWS sewer main trench restoration. SAWS sewer lateral excavation and installation completed, trench restoration. SAWS sewer manhole trench restoration at Broadway & McCullough.
  • Broadway (McCullough Avenue to 4th Street): AT&T utility duct bank trench restoration. CPS utility duct bank trench restoration. SAWS sewer manhole trench restoration at Broadway & 4th Street.
  • Broadway (4th Street to 3rd Street): AT&T manhole, and utility duct bank installation and trench restoration. CPS utility duct bank installation and trench restoration. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (3rd Street to Pecan Street): AT&T manhole, and utility duct bank excavation and installation. CPS utility duct bank excavation and installation. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (Pecan Street to Travis Street): AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation.
  • Broadway (Brooklyn Avenue to 8th Street): Planning SAWS sewer main excavation and installation. Planning SAWS sewer lateral excavation and installation.
  • Broadway (8th Street to 9th Street): Planning SAWS sewer main excavation and installation. Planning SAWS sewer lateral excavation and installation.
  • Removed trash and hauled away the debris.

June 2021 Construction Activities

The contractor continues installation of AT&T duct bank work through the Broadway corridor, which is associated with the $42 Million, 2017 Bond Project. Businesses and residents have sidewalk and parking lot accessibility.

Construction began on July 2020 and will be substantially complete by December 2023. For ease of reference, a map of the closures and detour routes is provided below.

  • Broadway (Brooklyn Avenue to 6th Street): AT&T & CPS trench restoration completed. SAWS sewer main excavation.
  • Broadway (6th Street to McCullough Avenue): AT&T & CPS trench restoration. SAWS sewer main completed. SAWS sewer lateral excavation and installation. SAWS sewer manhole installation at Broadway & McCullough.
  • Broadway (McCullough Avenue to 4th Street): AT&T utility duct bank restoration. CPS utility duct bank excavation, installation and trench restoration. SAWS sewer main completed. SAWS sewer laterals completed. SAWS sewer manhole installation at Broadway & 4th Street.
  • Broadway (4th Street to 3rd Street): AT&T manhole, and utility duct bank excavation and installation. CPS utility duct bank excavation and installation. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (3rd Street to Pecan Street): AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (Pecan Street to Travis Street): Preparations for AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation.
  • Removed trash and hauled away debris.

May 2021 Construction Activities

  • Broadway (Brooklyn Avenue to 6th Street): AT&T & CPS trench restoration. SAWS sewer main excavation.
  • Broadway (6th Street to McCullough Avenue): AT&T utility duct bank completed. CPS utility duct bank completed. AT&T & CPS trench restoration. SAWS sewer main completed. SAWS sewer lateral excavation and installation.
  • Broadway (McCullough Avenue to 4th Street): AT&T utility duct bank completed. CPS utility duct bank excavation and installation. SAWS sewer main completed. SAWS sewer laterals completed. SAWS sewer manhole installation at Broadway & 4th Street intersection.
  • Broadway (4th Street to 3rd Street): AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation. SAWS sewer manhole removal at Broadway & 3rd Street intersection. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (3rd Street to Pecan Street): Preparations for AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation. Preparations for SAWS permanent sewer lining installation inside existing sewer main.
  • Broadway (Pecan Street to Travis Street): SAWS sewer manhole work at Broadway & Pecan intersection. Preparations for AT&T manhole, and utility duct bank excavation and installation. Preparations for CPS utility duct bank excavation and installation.
  • Removed trash and hauled away debris.

Road Closures

Brooklyn Avenue to 4th Street:

March 4, 2021 thru April 26, 2021

 

Brooklyn Avenue to Pecan Street:

April 26, 2021 thru May 17, 2021

The contractor continues installation of AT&T duct bank work through the Broadway corridor, which is associated with the $42 Million, 2017 Bond Project. Businesses and residents have sidewalk and parking lot accessibility.

 

Broadway Road Closure

Brooklyn Avenue to 4th Street

3.4.21 thru 4.26.21

Click here for a larger map

Construction began on July 2020 and will be substantially complete by December 2023. For ease of reference a map of the closures and detour routes is provided below.

 

Broadway Road Closure

Brooklyn Avenue to Pecan Street

4.26.21 thru 5.17.21

Click here for a larger map

Updates for March 2021

The contractor continues installation of AT&T duct bank work through the Broadway corridor, which is associated with the $42 Million, 2017 Bond Project. Businesses and residents have sidewalk and parking lot accessibility. 

Construction began on July 2020 and will be substantially complete by December 2023. For ease of reference a map of the closures and detour routes is provided below. 

Planned activities for the next 4+ weeks:

The contractor continues installation of AT&T duct bank work, SAWS sewer, and CPS network construction through the Broadway corridor, which is associated with the $42 Million, 2017 Bond Project. Businesses and residents have sidewalk and parking lot accessibility.

Construction began on July 2020 and will be substantially complete by December 2023. For ease of reference, a map of the closures and detour routes is provided below.

 

Activity Estimated Date*

Broadway (E. Jones Avenue to 9th Street): Continue roadway reconstruction. Continue street, curb, sidewalk and driveway approach excavation. Begin storm drain pipe installation, and curb inlet installation at E. Jones intersection, and 10th Street intersection. Begin CPS manhole installation at E. Jones intersection, and 10th Street intersection. Begin pedestrian light foundation footings, conduit and electrical installation.

April 2022

Broadway (9th Street to Brooklyn): Continue roadway reconstruction. Continue street, curb, sidewalk and driveway approach excavation. Begin pedestrian light foundation footings, conduit and electrical installation.

April 2022

Broadway (Brooklyn to 6th Street): Continue SAWS water main excavation, installation, and tie-in. Continue SAWS water service excavation, and installation. Begin roadway reconstruction. Begin street, curb, sidewalk and driveway approach excavation.

April 2022

8th Street (N. Alamo Street to Avenue B): Continue CPS overhead utility to underground installation.

April 2022

9th Street (N. Alamo Street to Avenue B): Planning CPS overhead utility to underground installation.

April 2022

10th Street (N. Alamo Street to Avenue B): Continue CPS overhead utility to underground installation.

April 2022

North Alamo Street (McCullough Avenue to Travis): Street maintenance and clean-up work.

April 2022

Avenue B (McCullough Avenue to 10th Street): Continue forming new curb, sidewalks, driveway approaches, and wheel chair ramps. Begin tree illumination conduit installation.

April 2022

Throughout project: Continue AT&T telecommunication line installation. Remove trash, and haul away debris.

April 2022

Thank you for your patience as we improve your community!

*ALL WORK IS SUBJECT TO FAVORABLE WEATHER CONDITIONS

If you have questions about the project, please contact:

Joey Doctor
Capital Projects Officer
Public Works Department (PWD)
(210) 207-8415 or joe.doctor@sanantonio.gov 

After working hours or weekends, please call 311 or (210) 207-6000